Construction of swimming pool is already completed.
Land Development
Land development at sector 1 is already completed while sector 2A is at 78% completion.
Model Units
First batch (3 units) - Actual percentage of completion is at 95%.
Second batch (4 units) - Actual percentage of completion is at 55%.
Third batch (5 units) - Actual percentage of completion is at 25%.
House Construction
House construction at sector 1 is already completed.